Embodied carbon · live project tracker

Morgan

Job C5690 · PhoenixMe · updated 17/11/2026

IDSL
9.256tCO₂e to date13 deliveries
8.44tonnes of ductwork
12.721tCO₂e savedX-Carb steel vs standard
7.427tCO₂e in October 2026latest month

Month by month

Material (EPD)DeliveryHover a month for figures
02.557.510Sep 26Oct 26

Job to date

MaterialDeliveryTotal
Rectangular7.5590.2797.838
Spiral1.4070.0111.418
Total tCO₂e8.9660.2909.256

8.439 t of ductwork · 12.721 tCO₂e saved (X-Carb)

By month

MonthDeliveriestCO₂eRunning total
September 202641.8301.830
October 202697.4279.256

Deliveries

How this is worked out. Material carbon = tonnes delivered × the supplier’s EPD factor (tCO₂e per tonne). Delivery carbon = the delivery vehicle’s CO₂ per mile × the round-trip road miles from the supplier’s depot to site, once per delivery. The saving compares rectangular ductwork made from X-Carb steel with the same tonnage of standard steel. Every delivery is checked by IDSL against its delivery note before it counts. Figures are tCO₂e.

Imperial Ductwork Services Ltd · CarbonFlow · 17/11/2026 09:32